EQUIPMENT VALIDATION.


Equipment certification customer city skyline photograph.


Introduction to Equipment Certification.

Compliant equipment validation can be quite simple to achieve providing the procurement stage has been thoroughly investigated and concisely documented in accordance with a company approved process (SOP).   The procurement process normally starts with the production of a documented requirement or group of requirements (URS). For new builds this must be incorporated into the originating validation or project plan (VP)

For existing facilities this should take the form of a CHANGE REQUEST (CR).  As soon as management has agreed to proceed with the CR, approval should be issued to produce a VP.  This plan must be all encompassing.  It must give assurance that all aspects of the proposed CR have been studied and the CR impact on existing facilities, utilities, product and personnel have been defined and the appropriate corrective or support actions planned for.  A fully detailed User Requirements Specification (URS) can now be authored reviewed and published.  Since developing the URS may raise problems that could not be anticipated when the VP was raised; there must now be a VP review to ensure all aspects of the final approved URS are authorized and planned for.    

With an approved VP in place, a start can be made in authoring, reviewing and publishing the qualification protocols that are required to verify that all the requirements documented in the URS and all applicable cGMP requirements are complied with.  These are:

Where vendor developed Functional Specifications (FS) and or Design Specification (DS), are available they should be reviewed and referenced in the VP.  Where these documents are not available a DS or FS may have to be retrospectively developed.  The Design Qualification (DQ) must be used to verify that this FS or DS (if proceeded with) will deliver a system compliant with all requirements in the URS and the applicable cGMP rules and regulations. The execution of this DQ must verify that the proposed design will;

  • Perform as specified in the URS.
  • Conform to all mandated cGMP requirements.
  • Operate in a manner safe to the product, and the operations staff. 

The installation of each validatable system must be subjected to, and satisfy, a pre-approved Installation Qualification (IQ) protocol.  When the requirements of the IQ have been satisfied, all aspects of the operational capabilities of each system must be fully challenged and verified by the execution of a pre-approved Operational Qualification (OQ) protocol.  As soon as the executed IQ and OQ protocols having been reviewed and approved, a pre-approved Performance Qualification (P1Q) protocol or Process Qualification (P2Q) (this requirement will be documented in the VP) must be issued for execution.  The execution of this PQ must verify that the system performance requirements, as specified in the URS have been achieved, and that the system operates in a manner safe to the product and production personnel.   



All validation relates to a regulated product either directly or indirectly.

Direct equipment validation; is the verification of the recipe (in a medical device, the design).  Verification that the said ingredients (design) processed (manufactured) in accordance with the recipe (design specification) will consistently produce the final product to the efficacy that is specified.

Indirect equipment validation; is the equipment validation along with production and process equipment qualification.  Verification that the said equipment, consistently produces the product (or product part) within defined specifications.


Validation Implementation and Progression.

You have a new product and you are tasked with the equipment validation for the entire project.  Along with the facilities and utilities, being put into place to manufacture this product.

Task 1. Obtain all available equipment / system information.


Diagram 1.  FLCV.

This schematic depicts the inter-relationship between the various documents required for successful Equipment Validation.


Task 2.  Validation Plan

Validation Master Plan (VMP) gives an overall depiction of the company facilities, along with the management structure, and details of how cGMP is, or is to be, integrated with all company activities.   On the other hand the Equipment Validation Plan (VP) is used to manage equipment validation projects that are smaller in size and have easily defined boundaries. Raise the appropriate Validation (Master) Plan (VMP/VP) as described in http://www.validation-online.net/validation-master-plan.html or purchase and download one from http://quality.validation-online.net  Complete all requirements and circulates draft copy of document for peer review.

Incorporate all circulation comments and submit for approval.

Issue document for project management use.


Task 3.  Introduction to Matrix.

Raise a Validation Documentation Matrix (10000002) chart as described in http://www.validation-online.net/validation-documentation-matrix.html or purchase and download one from http://quality.validation-online.net and in the ‘description’ column, list all equipment that requires to be reviewed for validation assessment.

As far as possible where equipment operates as a system, it should be listed as a system.  Where it does not, or can not, then list individual equipment.  For each listing raise individual User Requirement Specifications.  Either author one in accordance with http://www.validation-online.net/user-requirements-specification.html or purchase and download one from http://quality.validation-online.net/

This graphic depicts an Equipment Validation Matrix sheet.

Right click in each cell of the spreadsheet, and open a Comments page. Insert into the comments page;
Person responsible for the document:
Date started:
Date first review:
Date final review:
Date issued:
Date executed:
Date execution reviewed & accepted.
The above data would normally be monitored and controlled from a planning schedule (such as Microsoft Project as shown on Diagram 3), however it is important to have this matrix in place as the master record of all project details.



Diagram 3. Plan.

This graphic depicts a Validation plan layout as required for successful Equipment Validation.

Task 4.  Matrix Population.

As items are added to the matrix, a unique number is allocated to each one, in Column 1.  This is the equipment validation number, individual protocols are subsequently identified by adding the document acronym to the end of the unique number.  This way all validation documents for an item have the same identifying number.  Progressively subject each item listed in the matrix, to the questions in the Validation Risk Assessment (VRA), which should either be authored in accordance with http://www.validation-online.net/validation-risk-assessment.html  or purchased and downloaded from http://quality.validation-online.net/ . 

As each piece of equipment completes the VRA and is given a risk rating, and an assessment for part 11 compliance, enter these ratings into column seven of the matrix, in the row allocated for the equipment.  Format, (risk rating)(Y or N for part 11 compliance).

Note.

Risk Assessment (RA) in the pharmaceutical / biotech / medical device validation industry, is often misunderstood.  In regulated industries RA’s are used for a many different purposes.   In our case we are only considering the use of an RA to justify the depth and scope of our validation requirement.  As such the VRA has to simply ascertain; what scope of validation this system / equipment qualification must be subjected to, to ensure it is correctly validated, and whether the system has to conform to 21 CFR Part11.

 

Task 5. User Requirement Specification (Sections 1)  (URS).

For each system/item listed in the matrix raise a user requirements specification as (URS) as described in http://www.validation-online.net/user-requirements-specification.html or purchase and download one from http://quality.validation-online.net.   Register each URS by giving it a unique number and entering that number into the matrix column.

Circulate the registered URS templates to the individual equipment owners as specified in the project VP/VMP.  Request owners complete section one of URS.

 

Task 6. User Requirement Specification (approval),  (URS).

On complete of Section One requirements, the URS must be reviewed and approved.   The approved URS must then be forwarded to the procurement team.  It is the procurement team’s responsibility to ensure that each individual invitation to tender, has the appropriate URS attached.

Schematic sketch of the equipment validation documentation requirements.

Task 7.  Design Qualification (DQ).

Ensure all preceding documents are signed off and approved.

When all vendor (and in house) design proposals have been submitted, (received from in, or out of house sources) the accepted design, must be subjected to a DQ, to validate it is fit for purpose.  A Design Qualification (DQ) protocol must be raised

in accordance with http://www.validation-online.net/design-qualification.html or purchase and download one from http://quality.validation-online.net .

The approved DQ must be executed to validate that the design is robust and has been subjected to sufficient proof of concept testing, to establish that if proceeded with, it will satisfy the requirements listed in the URS. 

 

 

Task 8.  User Requirement Specification (Sections 2 ) (URS).

The URS top level functionality is further broken down into sub-functions in the Design Specification (DS).  The vendor must therefore complete Section 2, of the URS, documenting the relationship between the URS functionality and the actual design functionality.   This is required to enable compliance with the requirement for maintaining the traceabilty from URS to software code, as further described in Task 9.

 

Task 9.  User Requirement Specification (Sections 3.) (URS).

Task 9 only applies where the equipment / system uses software.  The original Section 1, of the URS completed by the end user, detailed the top level functionality required.  Section two completed by the vendor detailed the sub-functions required to enable section 1 functions.  Section 3, completed by the code writers must detail the line or groups of lines required for each function and sub-function.

 

Task 10.   Installation Qualification.

Raise an Installation Qualification as described in http://www.validation-online.net/installation-qualification.html or purchase and download one from http://quality.validation-online.net/  Complete all requirements and circulates draft copy of document for peer review.

Incorporate all review comments and submit for approval.

Ensure all preceding documents are signed off and approved, prior to executing this document.

Issue document for execution.

Review executed document.

Produce summary report.

 

Task 11.  Operational Qualification.

Raise an Operational Qualification as described in http://www.validation-online.net/operational-qualification.html, or purchase and download one from http://quality.validation-online.net/  Complete all requirements and circulates draft copy of document for peer review.

Incorporate all review comments and submit for approval.

Ensure all preceding documents are signed off and approved, prior to executing this document.

Issue document for execution.

Review executed document.

Produce summary report.

 

Task 12.  Performance Qualification.

Raise an Performance Qualification as described in http://www.validation-online.net/performance-qualification.html, or purchase and download one from http://quality.validation-online.net/.  Complete all requirements and circulates draft copy of document for peer review.

Incorporate all review comments and submit for approval.

Ensure all preceding documents are signed off and approved, prior to executing this document.

Issue document for execution.

Review executed document.

Produce summary report.


EQUIPMENT VALIDATION


SEARCH AND FIND
YOUR DOCUMENT.




More and more New Start Companies are demanding that complete validation document packages are used. Just think - all the documentation in place on day one. CLICK HERE for NEW START package deals.


SOP for Spreadsheet Creation.

Why does something as simple as a spreadsheet figure in so many regulatory citations? Good question; and at times a difficult one to answer. When you ask a group of compliance personnel the same question you will be informed that Excel cannot be validated because it does not seal the original copy (of the spreadsheet), allows the original to be modified and has an audit trail that can be disabled. All true, but none of these problems interfere with your ability to validate that the spreadsheet is fit for purpose. They only preclude you from using the spread sheet as a compliant repository for any data that has to be store in compliance with 21 CFR Part 11.
If the spreadsheet is signed off and dated by the user, their supervisor and QA, it becomes regulatory acceptable data stored in hardcopy, and Part 11 does not apply.
After numerous requests for this, we have launched our brand new SOP for Spreadsheet Creation to cover these and other known target points that the regulators consistently hone into as soon as they find that spreadsheets are being used. Use this Spreadsheet Creation SOP to ensure that you create spreadsheets that are validatable. Then use our spreadsheet validation pack to validate them.

SOP for Spreadsheet Creation. -- $125.00

Quantity

SOP Equipment Validation.

The SOP for Computer Equipment Validation continues to be an extremely popular document. This document leads you through the validation process, from the URS to the final P2Q.


Purchase your copy now at Special Price of $22.00.
Quantity

Equipment combined IQ/OQ/PQ Protocol.

This combination protocol has been produced in response to several hundred reader suggestions we received in our ‘Suggestions Section’. It has been carefully designed to make it the preferred choice for Process and Laboratory stand alone equipment. It is interactive, easy to use and suitable for all mixes of equipment with and without software.
The IQ section establishes documented verification that key aspects of the equipment adhere to approved design intentions and that the recommendations of the manufacturer have been suitably considered. The OQ section establishes that there is documented verification that the installed system functions as specified and that there is sufficient documentary evidence to demonstrate this. The PQ section gives documented verification that the equipment performance in its normal operating environment is consistently exactly as specified in the URS.

Equipment Combined IQ/OQ/PQ Protocol (Issue-2). -- $159.00
Quantity

Validation Risk Assessment.

It now appears that the current FDA Guidance rules pertaining to 21 CFR Part 11 may be with us for a longer time than was originally anticipated. So we have incorporated the guidance suggestions in their latest guidance document, into our current Validation Risk Assessment (now issue 10), which is now available for immediate download. This VRA document now comes with a downloadable matrix for registering the justification for all your Part 11 assessments as this is now a mandatory requirement.



Validation Risk Assessment (Issue10.) -- $125.00
Quantity